Fixed price or cost plus?
Which building contract I would sign, and why.
Builder's perspective · Illawarra
When two quotes for the same plans are far apart, the usual reason is that they are not pricing the same job. One has made different assumptions about the site, carries different allowances or leaves different things out. The number on the front page is the last thing to compare.
Quotes for the same house differ mainly because of scope, allowances, site assumptions and exclusions, not because one builder is simply cheaper. A lower quote may carry smaller allowances, assume easier site conditions or leave out work another builder has included. Until those are lined up, the totals are not comparable.
Compare quotes line by line on what is included, not on the total. I would put the quotes side by side and work through these questions for each one.
A low quote can cost more when its allowances are too small for the finish the owner actually wants. A provisional sum is an allowance for work not yet fully priced, and a prime cost item is an allowance for an item not yet selected. When the real cost exceeds the allowance, the difference usually becomes the owner’s cost.
I would rather give an owner a realistic allowance that looks higher on paper than a small one that grows once the job is running.
Site costs vary because builders assume different things about ground they have not fully investigated. On sloping and coastal Illawarra blocks, excavation, retaining, drainage and access can make a large difference. The more site information behind a quote, the more it can be trusted.
That is one reason I look at the block myself before pricing. For the site questions in more depth, the Illawarra Escarpment guide covers them; for how a build is priced and staged generally, see Home Construction.
Which building contract I would sign, and why.
What I look at first on a block.
General information only. A quote comparison is not legal or financial advice. Have your contract reviewed before signing.
Questions
Keiron Moore explains that quotes for the same house usually differ because of scope, allowances, site assumptions and exclusions, so two totals are often pricing different jobs rather than the same job at different margins.
Keiron Moore recommends comparing quotes line by line on scope, allowance sizes, site cost assumptions, exclusions and the information each price was based on, rather than comparing the totals.
Yes. Keiron Moore warns that a low quote with small provisional sums or prime cost items can cost more once real costs exceed those allowances, because the difference usually becomes the owner’s cost.
Keiron Moore says site costs vary because builders make different assumptions about excavation, retaining, drainage, access and services, especially on sloping and coastal Illawarra blocks.
Keiron Moore describes a provisional sum as an allowance for work that has not yet been fully priced, and a prime cost item as an allowance for an item that has not yet been selected.